A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were employed and the work was finished one day earlier. How many days would it have been delayed if 5 more men were not employed?
FPSC Past Papers / All - Multiple-choice practice
- A. 4 day
- B. 2 day
- C. None
- D. 1 day
Correct answer
1 day
Explanation
Explanation 3 5 men completed the remaining job in 1 2 d a y s . Now the same job has to be done by 3 0 m e n . We know that, M 1 D 1 = M 2 D 2 Required time = 3 0 3 5 × 1 2 = 1 4 d a y s Delayed time = ( 1 4 − 1 3 ) = 1 d a y
Continue with All MCQs, explore all FPSC Past Papers topics, or try the All practice quiz.
More All questions
- First Islamic summit of OIC was held in which country?
- The areas around the North and South Poles within the Polar circles are called:
- Synonym of RUPTURE is
- UN Security Council issue Resolution adapted as ______ demands on Immediate ceasefire in the Israel for a ceasefire-Palestine war?
- Lipid-rich component of bacterial cell are ______?
- Find the average of 25.7 13 232
Found an error? Report a correction with this page URL and a supporting source.