A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were employed and the work was finished one day earlier. How many days would it have been delayed if 5 more men were not employed?

FPSC Past Papers / All - Multiple-choice practice

  1. A. 4 day
  2. B. 2 day
  3. C. None
  4. D. 1 day

Correct answer

1 day

Explanation

Explanation 3 5 men completed the remaining job in 1 2 d a y s . Now the same job has to be done by 3 0 m e n . We know that, M 1 ​ D 1 ​ = M 2 ​ D 2 ​ Required time = 3 0 3 5 × 1 2 ​ = 1 4 d a y s Delayed time = ( 1 4 − 1 3 ) = 1 d a y