If 6 men take 15 hours to complete a job, how many hours will 10 men take to complete the same job?
FPSC Past Papers / All - Multiple-choice practice
- A. 10 hours
- B. 8 hours
- C. 9 hours
- D. None of these
Correct answer
9 hours
Explanation
Explanation To find the number of hours 10 men will take: First, find the total work hours for 6 men: 6 men * 15 hours = 90 man-hours Now, divide the total work hours by 10 men: 90 man-hours / 10 men = 9 hours