If 70 men can work in 35 days, 40 men complete this work in days?

FPSC Past Papers / All - Multiple-choice practice

  1. A. 61.25
  2. B. 40
  3. C. 80.50
  4. D. 50

Correct answer

61.25

Explanation

Explanation Find how many man-days to complete the road: 70*35 = 2450 man-days Let d = days required for 40 men to do it. 40d = 2450 d = 40 2450 ​ = 61.25