If 80 men dug 4 holes in 12 months, how many men would be required to build 6 houses in months?

FPSC Past Papers / All - Multiple-choice practice

  1. A. 360 men
  2. B. 370 men
  3. C. 380 men
  4. D. 410 men

Correct answer

360 men

Explanation

Explanation 1/240 * n * 4 = 6 becomes: 1/240 * 360 * 4 = 6 we simplify to get: 6 = 6 confirming that our calculation of the number of people required is good. the answer is that it would require 360 men to fill 6 holes in 4 months.