Two classrooms are to be built in a school and planned that 8 masons and labours shall complete them is 20 days. If the number of workers is increased up to 10, how many days will be taken in the completion of work?
FPSC Past Papers / All - Multiple-choice practice
- A. 15 days
- B. 26 days
- C. 16 days
- D. 36 days
Correct answer
16 days
Explanation
Explanation 8 men can do work = 20 days 1 man can do this work = 8*20 10 men can do that work = [8*20]/10 =16 days
Continue with All MCQs, explore all FPSC Past Papers topics, or try the All practice quiz.
More All questions
Found an error? Report a correction with this page URL and a supporting source.