40 men can finish a work in 25 days. In how many days, 25 men will finish the same work?

FPSC Past Papers / All - Multiple-choice practice

  1. A. 30 days
  2. B. None of these
  3. C. 40 days
  4. D. 50 days

Correct answer

40 days

Explanation

Explanation 40 men finish the work in 25 days Total work = 40 men * 25 days = 1000 man-days Now, 25 men will finish the work: 1000 man-days / 25 men = 40 days