If 20 men can do a piece of work in 8 days, then how many men can finish the same work in 10 days?
FPSC Past Papers / All — Multiple-choice practice
- A. 16
- B. 15
- C. 18
- D. 17
Correct answer
16
Explanation
Explanation 20 men complete the work in 8 days Total work = 20 men * 8 days = 160 man-days Now, to complete the work in 10 days: 160 man-days / 10 days = 16 men