If 15 men do a piece of work in 8 days. How many men will finish it in 10 days?
FPSC 5 Years Past Papers Subject Wise (Solved With Details) / All — Multiple-choice practice
- A. None of these
- B. 14
- C. 8
- D. 12
Correct answer
12
Explanation
Explanation 15 men complete the work in 8 days Total work = 15 men * 8 days = 120 man-days Now, to complete the work in 10 days: 120 man-days / 10 days = 12 men