If 15 men do a piece of work in 8 days. How many men will finish it in 10 days?

FPSC 5 Years Past Papers Subject Wise (Solved With Details) / All — Multiple-choice practice

  1. A. None of these
  2. B. 14
  3. C. 8
  4. D. 12

Correct answer

12

Explanation

Explanation 15 men complete the work in 8 days Total work = 15 men * 8 days = 120 man-days Now, to complete the work in 10 days: 120 man-days / 10 days = 12 men