If 5 men complete a work in 8 days, how many men are required to complete the same work in 10 days?
Verbal & Non Verbal Intelligence Test MCQs PDF / Verbal Intelligence Test MCQs — Multiple-choice practice
- A. 4
- B. 6
- C. 8
- D. 2
Correct answer
4
Explanation
Explanation - Total man-days = 5 × 8 = 40 - Men needed to do the same work in 10 days = 40 ÷ 10 = 4
Continue with Verbal Intelligence Test MCQs MCQs, explore all Verbal & Non Verbal Intelligence Test MCQs PDF topics, or try the Verbal Intelligence Test MCQs practice quiz.
More Verbal Intelligence Test MCQs questions
- A series contains values 4, 4, 4, 4, 4, 4. Its standard deviation is?
- Round 3.864 to the nearest tenth.
- What is the square root of 13 (√13)?
- A jar has 5 marbles, 1 of each of the colors red, white, blue, green, and yellow. If 4 marbles are removed from the jar, what is the probability that the yellow one was removed?
- If 2b -5 =6 what is the value of b?
- Identify the odd one : February April June July
Found an error? Report a correction with this page URL and a supporting source.