If 5 men complete a work in 8 days, how many men are required to complete the same work in 10 days?

Verbal & Non Verbal Intelligence Test MCQs PDF / Verbal Intelligence Test MCQs — Multiple-choice practice

  1. A. 4
  2. B. 6
  3. C. 8
  4. D. 2

Correct answer

4

Explanation

Explanation - Total man-days = 5 × 8 = 40 - Men needed to do the same work in 10 days = 40 ÷ 10 = 4