15 men were hired to plough a piece if land in 10 days. To complete the same job in three days more number of men is required _____?

PPSC 5 Years Past Papers Subject Wise (Solved with Details) / All - Multiple-choice practice

  1. A. 30
  2. B. 35
  3. C. 40
  4. D. 50

Correct answer

35

Explanation

Explanation 15 men × 10 days = M2 × 3 days M2 = 50 More men = 50 - 15 = 35 Last verified on 08-03-2026