If 16 workers complete a task in 40 days. The number of workers required to complete the task in 80 days is ____?
IBA STS Screening Test Bps 05 to 15 Past Papers and Syllabus / All — Multiple-choice practice
- A. 10
- B. 12
- C. 20
- D. 8
Correct answer
8
Explanation
Explanation More days means less workers needed (inverse relation) 16 workers × 40 days = x workers × 80 days x = (16 × 40)/80 = 8 workers